The proof in practice.

OPENLY Valley Widnau breaks records

Switzerland

Valley Widnau

Switzerland Valley Widnau

 

Pioneering work

The driving force behind the Openly Valley Widnau pilot project was to prove that climate-efficient - or with carbon capturing even climate-neutral - construction is possible.

Openly Valley Widnau achieves around 5.5 kg of CO2 emissions during construction per m2 of energy reference area, putting it in the same global league as Living Places in Copenhagen by VELUX with Effekt Architekten (winner of the MIPIM Award 2024) and Hortus by Herzog & de Meuron, albeit without underground parking.

The big difference: Openly makes this knowledge available worldwide as a building system in order to achieve the greatest possible impact. Not every client and not every architecture firm has to reinvent everything.

We are driven by climate change, because 25% of global annual CO2 emissions come from the construction industry. As a society, we need to switch to fossil-free and, if possible, cement-free and local building materials that are renewable or can be reused.

Andy Keel

Facts about OPENLY
Valley Widnau

Total project volume: CHF 20 million (30 apartments)
Developer:
OPENLY AG
General planner & component development
: OPENLY AG & Schoeb AG
Building application stage 1: Baumschlager Eberle Architekten
Lead architects: Sandra Schuster & Jürgen Oswald
Color design: Meerevilla
Specialist planners & construction management: See Openly Partner

Stage 1: 3082m2 GFA (2267 SFR), 19 condominiums sold* and occupied
Stage 2: Planned by Valley-Architects
Execution 2025 with 1150m2 SFR, 11 apartments

Key Facts OPENLY Stage 1:

Construction costs: approx. 3,800 CHF/EUR/m2 floor area

CO2 balance creation: approx. 5.5 kg/EBF. With CO2 storage, backed up with certificates, the project already achieves net zero on occupation. See provisional CO2 balance

Heating and hot water energy requirement: approx. 31,000 KWH (= approx. 14KWH/m2 net floor area)
PlusEnergyHouse Annual yield PV system: approx. 85,000 KWH (covers heating with heat pump, household electricity and approx. 200,000 electric car kilometers)

Number of employees: 8 OPENLY & approx. 20 specialist planners
Construction time stage 1: 13 months (start of excavation to occupation)
Planning time: 17 months

Photocredit: Jens Ellensohn
High res download: Openly/media